Recommendations
| Planning |
Cluster Design. The cluster design helped
to reduce overall imperviousness, and increase open space.
A cluster approach is recommended for future developments.
LID-based Regulations. Because many waivers
were required for the construction of this project, an LID
ordinance is recommended to facilitate adoption of this approach
in other towns.
Disconnect Stormwater. The percentage of
impervious coverage has been related to water quality and habitat
impairments. As part of the low-impact development approach,
disconnection of stormwater sources should be considered at
the planning phase. Common disconnects include gutter design
(to ensure that downspouts drain to pervious surfaces), road
and driveway design. By emphasizing disconnected stormwater,
the thresholds identified for water quality impacts from traditional
developments may not apply. |
| Construction |
Compaction. Soil compaction due to heavy
equipment use of a temporary access road caused problems
with infiltration in rain gardens and swales. Therefore,
it is recommended that soil compaction be kept to a minimum,
and that hard-surface roads are used for access during construction.
Undisturbed Soils. To help maintain the overall
infiltration capacity of the soils on the site, it is recommended
that as much of the site’s soils and vegetation as possible
is left undisturbed.
On-site Supervision. Because LID practices
are still fairly new and contractors are unfamiliar with their
installation, it is recommended that a person versed in installation
of LID techniques is on-site during construction. In addition,
it is imperative that this person has the ability to make adjustments
to the plan in the field, as necessary.
Earthen Berm. The installation of the earthen
berm to reduce export of sediment and runoff worked well, and
is a recommended construction best management practice.
Grassed Swales. Due to the fact that grassed
swales are vegetated systems and are vulnerable to erosion
until stabilized, it is recommended that temporary erosion
and sedimentation controls are implemented when swales are
installed. See the Connecticut Guidelines
for Soil Erosion and Sediment Control (DEP Bulletin 34) for
specific recommendations.
Soil Testing. Contractors are accustomed
to applying a starter fertilizer to loam when seeding a lawn.
This practice occurred at the site, despite the fact that soil
tests showed that no fertilizer was needed. Therefore, it is
recommended that a soil test is performed when loam is applied
to swales or lawns, and that the contractor follows the recommendations.
More broadly, soil tests do not include a test for nitrogen,
so even if homeowners or contractors have a soil test done,
recommendations for nitrogen application are not provided.
It is recommended that a nitrogen test be a component of standard
soil testing. |
| Post-construction |
Education. The intensive one-on-one education
methods that are traditionally thought to produce the most
effective behavioral changes did not perform as intended.
The involvement of a social scientist might be helpful to
ascertain appropriate education methods.
Bioretention Maintenance. Maintenance of
the cul-de-sac bioretention area resulted in excessive weed
trimming with damage to shrubs. It is recommended that proper
maintenance techniques be implemented to ensure proper function,
aesthetics and plant health. Such techniques include maintenance
of flow paths, surface water storage capacity and mulching
to reduce weeds and the need for mowing.
Paver Maintenance. Due to the excessive loading
of wind-blown fine particles loaded on to the pavers before
construction was complete, the infiltrating ability of the
roadway was reduced. Therefore, it is recommended that if a
pervious surface has high loading of fine particles, the surface
should be maintained by vacuum suction and replacement of the
infill materials.
 |
| Image of a turf dam. |
Turf Dam. The turf has begun to creep over
the edge of the roadway in some places. Some consideration
should be given to avoid this growth, as it can channel water
down the roadway and prevent it from entering the swale.
Fire Hydrant. The fire hydrant on site was
flushed at one point, and the infill material on the roadway
was washed out in a large area. It is recommended that if this
practice is necessary, care should be taken to direct the flush
water away from the roadway and into an area that will not
erode.
Seed Mix. A special turf seed mix was used
at the site that had low fertilizer, water and maintenance
requirements. However, several homeowners reseeded large areas
with standard seed. Therefore, it is recommended that the use
of the special seed mixture is specified in the homeowners’ association
documents. |
| Monitoring |
Control. The use of the control watershed
was critical in this study to attribute the changes observed
to the construction and management practices used, without
bias from climatic variations. Therefore, the use of a similar
control is advised in future monitoring efforts.
Forested Control. The control used in this
project was a previously developed residential area. To make
direct comparisons with the pollutant export from undeveloped
areas, it would be helpful in future studies to include an
undeveloped control with strong protection measures to ensure undeveloped status during the duration of future study.
Sampling Methods. Although the continuous
automated sampling used in the project was highly successful,
relatively few event-based grab samples were taken. Grab sampling
is weather dependent, and is difficult to perform at a remote
site. Future projects should consider the proximity of the
site if grab sampling is desired. In addition, a local volunteer
could be enlisted to aid in collecting samples on evenings
or weekends.
Electric Power. Solar panels were used to
supply power at various times through the project. However,
the ability to connect to the power grid provided more stability
and gave more flexibility for sample preservation (i.e., the
use of small refrigerators). Future projects should consider
connections to the grid when possible. |
| Further Study Recommendations |
Groundwater Effects. Groundwater monitoring
was not performed as part of this study. However, the addition
of this type of monitoring would help to answer questions
about the fate and transport of pollutants as a result of
the LID infiltration practices used, versus traditional stormwater
methods.
Social Indicators of Behavior. The intensive
education methods used in this study did not provide the expected
results. Future watershed studies should include social scientists
to better understand the role of humans in a watershed.
Testing of Soils. Some soil testing was performed
as part of this study, however, a more intensive soil testing
effort would provide valuable information on the fate and transport
of pollutants.
Economics of LID. Economists should be involved in LID watershed studies to appropriately assess LID costs and benefits compared to traditional development. |
| Myths Refuted |
Winter Infiltration. Although no formal
seasonal analysis was performed to investigate BMP performance
during winter months, paired watershed analysis of the LID
subdivision indicated decreases in the runoff volume and
rate as compared to pre-development. In addition, field
observations indicated that the rain gardens, the grassed
swales and the paver road functioned as designed through
the winter months.
Frost Heaving of Pavers. Frequent concerns
are voiced about paver blocks heaving in the winter due to
frost penetration. The EcoStone® paver roadway has remained
in excellent condition, with no frost heaving noted. The installation
of a proper bedding material and storage layer to encourage
rapid infiltration into the subgrade is critical to this function.
Education. Typically, intensive, one-on-one
education methods are assumed to be the most effective means
to bring about changes in attitude and behavior. However, on
this project, this method did not bring about the desired behavior
changes. |
Back to Top
|